Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Availability control is not working for WBS element inspite of avtivation | Mirna | SAP PS - Project System | 2 | 11-30-2011 08:18 PM |
| problem with budget availability control | Zumba | SAP PS - Project System | 2 | 11-16-2011 12:00 AM |
| Need help with Orphaned BIBCTL jobs when DSO Activation fails | Pepa | SAP BW/BI | 3 | 08-25-2011 12:39 AM |
| Budget Availability Control For Internal Activities Confirmation | Ramma | SAP PS - Project System | 2 | 04-26-2011 09:01 PM |
| Auto extend, or not... | Lala | SAP BASIS | 2 | 09-09-2010 01:15 PM |
| Aprenda SAP! |
|
|
![]() |
|
|
Thread Tools | Display Modes |
|
#1
|
|||
|
|||
|
Hello Experts,
We are using SAP IM and SAP PS. Project is created from AR and budget is allocated through IM position. In this case, Availbility Control is not automatically activated and we are forced to activate the same using CJBV. Is there a way out to activate the AVAC automatically as it happens when we allocate the budget in CJ30 ? Awaiting your expert guidance. Thanks & Regards, Micro |
| Sponsors |
|
#2
|
|||
|
|||
|
Hi Micro,
In OPS9 transaction select the relevant budget profile and maintain the "Activation type" as 1 and check. Regards, Portal |
|
#3
|
|||
|
|||
|
Hi Portal,
Thanks for your reply. I had already maintained this setting. Regards, Micro |