SAP-Forum.ORG
   
This web site isn't affiliated with, sponsored by, or approved by SAP AG. Is only a SAP users community.

Go Back   SAP-Forum.ORG > SAP Forums > SAP PS - Project System

Similar Threads
Thread Thread Starter Forum Replies Last Post
Before creating the PO reserve the budget ERP SAP PS - Project System 2 12-14-2011 08:33 PM
Budget Report Lala SAP PS - Project System 2 05-01-2011 05:31 PM
Budget Revision Mirna SAP SD - Sales & Distribution 1 04-20-2011 01:52 PM
weekly budget vs. Actual Lala SAP Business Objects 1 03-08-2011 12:51 PM
Budget in PS koko SAP PS - Project System 0 04-07-2010 07:59 PM

Aprenda SAP!
Reply
 
Thread Tools Display Modes
  #1  
Old 01-03-2012, 11:56 PM
Ramma Ramma is offline
Senior Member
 
Join Date: May 2010
Location: California
Posts: 287
Default Budget Exceeded Error even after budget available in in CJ30

Hello Experts,

I have configured the PS-Budget. While creating PO I am getting below error
Code:
Item 010 WBS element PCS-0012 budget exceeded Message no. BP603 Diagnosis Budget was exceeded by 100,00 INR in document item 010 WBS element PCS-0012 .
When I am looking in T.code CJ30 I can see for year 2011 Rs.30,000/- is available still getting error. The budget profile is also configured correctly. I am not checking budget at a Released level.

What step I am missing here to check ? or my approach is wrong. When I am looking at CJI5 I am not getting even a single line item posted on WBS still how I am getting error?

Thanks and regards,
Ramma
Reply With Quote
Sponsors
  #2  
Old 01-03-2012, 11:57 PM
Lala Lala is offline
Senior Member
 
Join Date: May 2010
Location: Chicago
Posts: 394
Default Re: Budget Exceeded Error even after budget available in in CJ30

Hello Ramma,

Please check in CJ30 any budget is showing as distributable for that particular WBS Element.

Regards,
Lala
Reply With Quote
  #3  
Old 01-03-2012, 11:59 PM
Ramma Ramma is offline
Senior Member
 
Join Date: May 2010
Location: California
Posts: 287
Default Re: Budget Exceeded Error even after budget available in in CJ30

Hi Lala,

Yes, I can see the amounts in Distrubutable. Could you please tell me what does this mean?

Your guidance / inputs will be appreciable on this.

Regards,
Ramma
Reply With Quote
Entre a los Links relacionados
Reply

Bookmarks

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are GMT. The time now is 08:20 AM.


Powered by vBulletin® Version 3.7.4
Copyright ©2000 - 2012, Jelsoft Enterprises Ltd.
Forum Design By inferno