Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Allocation at component level | Zoom | SAP PP - Product Planning | 2 | 10-06-2011 07:08 PM |
| Is it possible to have Auxiliary Cost Component as Value Fields in COPA | Micro | SAP FI CO - Financials and Controlling | 2 | 01-26-2011 09:06 PM |
| Sub-con PO: Fetching char's for component | ERP | SAP MM - Material Management | 0 | 11-25-2010 11:28 PM |
| Communication between the abstract portal component | mohan_cbe | SAP Portal | 0 | 11-07-2010 01:03 AM |
| Client Copy - MM Movement Type Field Selection didn't copy | Zoom | SAP BASIS | 2 | 07-26-2010 09:29 PM |
| Aprenda SAP! |
|
|
![]() |
|
|
Thread Tools | Display Modes |
|
#1
|
|||
|
|||
|
Hi Experts,
We are using BOM Transfer in our projects. The issue is that when we create a new project as a copy of an old project the information in the Assignment Tap of the components is not being copied. And we would like to keep the information of the assembly and the main assembly of the item. Is this because of a system error? Or it is standard behaviour? Can be mended? Thanks a lot, Zumba |
| Sponsors |
|
#2
|
|||
|
|||
|
Hi Zumba,
While copying the desired project and creating a new project are you un-checking the "With activities" check box and also "Components" check box ?.If yes pls do not do that,once u copy the project in the template tab,make sure that both the "With activities" and the "Components" Check boxes are checked.i.e it's ticked. Please do that and check again. I hope this will solve your problem. Regards, Portal |
|
#3
|
|||
|
|||
|
Hi Portal,
I don't know which Template Tab do you mean. I'm copying the project from CJ20N, Project/New/Copy Project. Could you give a bit more of detail about how to do it? Thanks. Zumba |