SAP-Forum.ORG
   
This web site isn't affiliated with, sponsored by, or approved by SAP AG. Is only a SAP users community.

Go Back   SAP-Forum.ORG > SAP Forums > SAP PS - Project System

Similar Threads
Thread Thread Starter Forum Replies Last Post
Resource Rel Billing - VA43 - Account Assignment Zoom SAP PS - Project System 2 11-04-2011 04:33 PM
PO Dates mismatch between APO and R/3 Ramma SAP PP - Product Planning 2 10-26-2011 04:20 PM
Status profile and status change in opportunity Rampa SAP CRM 2 06-27-2011 10:03 PM
Prevent actual postings based on project dates ERP SAP PS - Project System 1 04-10-2011 11:21 PM

Aprenda SAP!
Reply
 
Thread Tools Display Modes
  #1  
Old 12-21-2011, 09:24 PM
Zumba Zumba is offline
Senior Member
 
Join Date: May 2010
Location: Colorado
Posts: 240
Default How to capture dates of attaining status REL, CNF for all steps in project?

Hi All,

I'm making a report where i need to capture dates of REL & CNF status of every step in a project. After entering project number/WBS element in table AFVC I'm getting object number OBJNR. But when same is entered in JCDS syatem says data doesn't exist. I'm able to view the same OBJNR in JEST where I get whether status is active or inactive.

I'm getting OBJNR for main project from PRPS & able to get dates of main WBS from JCDS.

My entire development is stucked due to this.

Please help.

Regards,
Zumba
Reply With Quote
Sponsors
  #2  
Old 12-21-2011, 09:26 PM
Golfi Golfi is offline
Senior Member
 
Join Date: May 2010
Location: Delaware
Posts: 824
Default Re: How to capture dates of attaining status REL, CNF for all steps in project?

Hi Zumba,

I think I can contribute something here:

First of all you need Object Number for each PS Operative Objects and you can get those from following tables:
Project Def: PROJ
WBS Element: PRPS
Network: AUFK
Activity: AFVC

Then I beleive you have to pass this OBJNR into table JCDS. Here you have filter out/remove STAT lines having INACT as X.
Also if some STAT line get repeated then consider highest Change Number line and accordingly make your I_TAB.

Now you have some STAT line with UDATE and UTIME. Now you can get these STAT description by passing these STAT into table TJ02Twith Language value as EN. Here you will get Status Description as well.

Please let me know whether it will work or not.

Regards,
Golfi
Reply With Quote
  #3  
Old 12-21-2011, 09:29 PM
Zumba Zumba is offline
Senior Member
 
Join Date: May 2010
Location: Colorado
Posts: 240
Default Re: How to capture dates of attaining status REL, CNF for all steps in project?

Hi Golfi,

Information which you have provided is known to me. My requirement is very simple.

Example if i release 1 of the project step on 10th december; & if i confirm the same step on 20th December; which are the 2 fields & respective tables where these 2 dates could be captured?

Please help.

Regards.
Zumba
Reply With Quote
Entre a los Links relacionados
Reply

Bookmarks

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are GMT. The time now is 08:26 AM.


Powered by vBulletin® Version 3.7.4
Copyright ©2000 - 2012, Jelsoft Enterprises Ltd.
Forum Design By inferno