Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| CJ40 cost not been updated in Planned cost report | Micro | SAP PS - Project System | 2 | 12-16-2011 08:23 PM |
| Determination of Production Order Type when Planned Order is Converted | Zumba | SAP PP - Product Planning | 2 | 10-18-2011 07:04 PM |
| No update of sales order 4xxxxxxxx from purchase order (error V1 154) | Rampa | SAP SD - Sales & Distribution | 2 | 09-13-2011 06:12 PM |
| Planned cost in cProject - PS integration | Lala | SAP PS - Project System | 2 | 04-13-2011 08:36 PM |
| Purchase Order List | Micro | SAP MM - Material Management | 1 | 12-20-2010 01:48 PM |
| Aprenda SAP! |
|
|
![]() |
|
|
Thread Tools | Display Modes |
|
#1
|
|||
|
|||
|
Hi experts,
We are using Easy Cost Planning (ECP) and we would like to know if it is possible to have the planned price copied to the purchase order document (or purchase requisition) created through Execution Services. We do not want to have a new price determination in the document. Is it possible? Thanks, Pepa |
| Sponsors |
|
#2
|
|||
|
|||
|
Hi Pepa,
Similar function was implemented for our company using Exits/BAPI for PR price. Was done by MM team. They achieved it through field exit on PRICE field within the network. Hope this could help. Regards, Mirna |
|
#3
|
|||
|
|||
|
Thanks Mirna.
We won't do it for now but is good to know. Regards, Pepa |