Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Different procurement tyeps for different requirements | Lala | SAP PP - Product Planning | 2 | 10-24-2011 08:06 PM |
| Email Alerts on CIF blocker | SAPMM | SAP PP - Product Planning | 2 | 10-07-2011 07:40 PM |
| CIF Location | Pepa | SAP PP - Product Planning | 2 | 09-30-2011 07:05 PM |
| Multiple Direct SAP requirements. | koko | SAP Job Offered | 0 | 04-29-2011 02:02 PM |
| Multiple Direct SAP requirements | koko | SAP Job Offered | 0 | 11-19-2010 12:09 PM |
| Aprenda SAP! |
|
|
![]() |
|
|
Thread Tools | Display Modes |
|
#1
|
|||
|
|||
|
Hello experts,
We want to transfer Planned Independent requirements from ECC to APO through CIF. Planner maintained the PIRs in Monthly periods. and CIF transfer happening successfully. However the Requirement date in APO product view showing as starting of the Month. For example: Forecasts maintained in ECC : M1- 2011 ---- 10000 M2- 2011----- 12000 When comes to APO Forecast requirement date/time set as: Req Date--------Time------Qty 01.01.2011-----03:00------10000 01.02.2011-----03:00------12000 but we want requirement date and time to be set to month end dates (want to see as below) Req Date--------Time--------Qty 31.01.2011------12:00 ------10000 28.02.2011------12:00-------12000 Can you please provide some useful hints on how to acheive this. Best Regards, Rampa |
| Sponsors |
|
#2
|
|||
|
|||
|
Hi Rampa,
Have you checked in ECC MD04 tcode? What is the date it is showing there? If in MD04 date of ind. requirement is showing same as APO then there is no problem it is expected behaviour. If not Try running CCR to correct inconsistency. Regards, Lala |
|
#3
|
|||
|
|||
|
Hi Rampa,
You need to use User Exit i.e CIFPIR02 on ECC side to convert the month into last day. Regards, Golfi |