#1
|
|||
|
|||
|
Dear Experts,
I'm working with Period lot size "W" with No. Of period 1 and the Period factor 1. I maintain this setting in Both location production Plant & Distribution Center I have Demand from Distribution Center 2014, when i run SNP Heuristic and after that PP/DS. The stock transfer coming before the End date of the PlOrd Start Date & Time: 11.11.2011 07:00:00 to 15:00:00 PReqRel Start Date & Time: 11.11.2011 07.:00:00 to 15:00:00 PlOrd Your help will be very appreciated. Thanks and regards, Mirna Last edited by Mirna; 10-24-2011 at 08:19 PM. |
| Sponsors |
|
#2
|
|||
|
|||
|
Hi Mirna,
Please check if you have checked the "Use period factor" box in Lot-size tab of product master. For scheduling in Re-order point planning this needs to be checked and also the period factor value has to be maintained. Regards, Golfi |
|
#3
|
|||
|
|||
|
Hi Golfi,
Thanks for your Response. Of course i cheked the use period factor to working with period lot size. Please advise. Regards, Mirna |