Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Alternative resource allocate to plan order. | ERP | SAP PP - Product Planning | 2 | 10-07-2011 07:34 PM |
| Sales Order does not show up at the resource level. | Micro | SAP PP - Product Planning | 2 | 09-30-2011 06:46 PM |
| Resource Consumption | Mirna | SAP PP - Product Planning | 1 | 09-20-2011 09:16 PM |
| Fixing Planned Order to one resource | Lala | SAP PP - Product Planning | 2 | 09-06-2011 10:53 PM |
| Automatic Alternate BOM Selection while creating Sales Order | SAPMM | SAP SD - Sales & Distribution | 1 | 04-06-2011 11:04 PM |
| Aprenda SAP! |
|
|
![]() |
|
|
Thread Tools | Display Modes |
|
#1
|
|||
|
|||
|
Hi all,
In PDS the '01' resource mode is on proirity 'A' but in the product heuristic run system is selecting the Mode 02 that is with the priority 'B'. System should assign the resorce '01' as its on higher priority, how can I do it? Thanks in advance, Zumba |
| Sponsors |
|
#2
|
|||
|
|||
|
Hi Zumba,
Can you check in strategy profile what is the setting defined for " Lowest mode priority"? Regards, Golfi |
|
#3
|
|||
|
|||
|
Thanks Golfi!
In the global settings for interactive planning, strtegy profile is SAP002 and in Strategy P. SAP 002 the Lowest Mode Priority is blank is this a information you are asking? if this is the reason then please help me in this area and elaborate the impact of this setting. Thanks in advance, Zumba |